Baker Blvd Construction

Post Date:01/03/2018 5:00 PM

The Texas Department of Transportation (TxDOT) has contracted with Ragle Construction to make improvements to Baker Blvd between Rufe Snow and Handley Ederville.

 

The improvements will consist of the following:

 

1. Right turn lanes at the Rufe Snow/Baker Blvd. and Handley Ederville/Baker Blvd. intersections;

2. Sidewalks along Baker Blvd. (north and south sides) from Handley Ederville to Rufe Snow;

3. Relocate Ash Park to intersect directly with Vance; &

4. Curb/gutter and drive approaches in various locations

 

The first phase of the improvements will consist of mobilizing and placing out barricades to manage traffic control. This will begin between now and this coming Monday, January 8th. Heavier equipment and contractor crews will be out next week with construction beginning immediately. The project is expected to last between 10 and 12 months.